By | Blog, Slider | No Comments

Site 1, barangay Agujo in Daanbantayan: The construction of the 74 houses and the Multi-Purpose Center have been completed. The site now needs site development (concrete roads and sidewalks, drainage and water distribution system etc) for families to be able to move in. FP-UA will be fundraising the P 3,300,000 needed to complete the site development of Site 1 in order to turn over the village to the beneficiary families as soon as possible. Site 2, barangay Paypay in Daanbantayan: The construction on Site 2 is well under way with 98 houses (out of 128) currently being built, and the site development 80% complete. The construction of the multi-purpose center and the clinic is expected to start this coming month. This site should be ready for turnover by June this year. Site 3, barangay Cayang in Bogo: The location for Site 3 has already been selected. This site will comprise…